2019年5月7日 星期二
2019 05 07 左永安顧問 PMP Exam: Earned Value Management - Part 3, Forecasting Completion 工業4.0 哈佛個案 精準訓練 職能基準 職能導向課程 左記歐洲商行 安永經營管理顧問集團 台北左府(無極)鳳清道德宮司 台大 台師大 EMBA 共通核心職能 專案管理 TTQS ICAP PMP WINE This is a three part lesson. Part 1 covers basic concepts, i.e. how to derive PV (Planned Value), EV (Earned Value) and AC Actual Cost. (These terms are also known as BCWS, BCWP and ACWP respectively.) Part 2 shows how to apply these items to calculate variances (SV - Schedule Variance, CV - Cost Variance, SPI - Schedule Performance Index, CPI - Cost Performance Index). Part 3 explains how Earned Value Management is used to forecast project performance by calculating EAC - Estimate at Completion, ETC - Estimate to Complete, VAC - Variance at Completion, and TCPI - To Complete Performance Index.
訂閱:
張貼留言 (Atom)
沒有留言:
張貼留言